Rates
What does digging a trench cost per metre?
Between € 18 and € 67 per linear metre, depending on the soil. Below is exactly where that difference comes from, what is and is not included, and what happens if the ground turns out worse.
The price depends on how many metres a digger achieves per hour, and that varies by a factor of four between soil types. Hence three classes rather than one average that leaves everyone unhappy.



| Class | Soil type | Recognisable by | Output | Per m¹ |
|---|---|---|---|---|
| 1 — Light | Sand, sandy ground, loose garden soil, unpaved | Dry, loose, falls off the spade | ± 4 m¹/hour | € 18 |
| 2 — Heavy | Sandy clay, clay, peat, wet or compacted ground | Sticks to the spade, has to be cut loose | ± 2 m¹/hour | € 33 |
| 3 — Obstructed | Rubble, stones, tree roots, old foundations, cable bundles | Every metre costs tool changes and muscle | ± 1 m¹/hour | € 67 |
All amounts excluding VAT. Includes digging, backfilling with the excavated material and compaction.
Dimensions
Other depths or widths
The base rate applies to 0.60 by 0.30 metres. Where the trench differs, the factor below applies to the rate of the relevant class.
| Dimension | Typically used for | Factor |
|---|---|---|
| 0.40 m deep × 0.30 m | Telecom and data, shallow garden cabling | × 0.75 |
| 0.60 m deep × 0.30 m | Low voltage, standard house connection | × 1.00 |
| 0.80 m deep × 0.30 m | Gas, and wherever the grid operator requires deeper | × 1.30 |
| 1.00 m deep × 0.30 m | Crossings, deeper-lying routes | × 1.60 |
| Width 0.40 m | Several ducts or cables side by side | × 1.25 |
| Width 0.50 m | Bundles, or where work has to be done inside the trench | × 1.50 |
Factors are cumulative: a trench 0.80 m deep and 0.40 m wide in class 2 comes to € 33 × 1.30 × 1.25 = € 53.63 per linear metre.
Surcharges
What is charged separately
Everything not in the base rate is listed here with an amount against it. So you know up front where a quotation can land, rather than afterwards.
| Item | Explanation | Rate |
|---|---|---|
| Paving or block paving | Lifting, stacking separately and relaying afterwards | € 12 / m¹ |
| Asphalt or concrete | Sawing and breaking out; reinstatement by a specialist | on request |
| Trial trench | At a crossing or where the position is unclear, per CROW 500 | € 85 each |
| Removal of surplus soil | Including transport and disposal of clean soil | € 28 / m³ |
| Supplying backfill sand | Where the excavated material is unsuitable for backfill | € 42 / m³ |
| Rush | Start within five working days of instruction | + 20 % |
| Evening, weekend or public holiday | Work outside regular hours on request | + 35 % |
| Minimum order | Per instruction, regardless of route length | 25 m¹ or € 450 |
Worked example
What a price looks like
A 120-metre fibre route along a back path: 70 metres of sand under paving, 40 metres of clay, and 10 metres alongside an old foundation.
| Line | Quantity | Rate | Amount |
|---|---|---|---|
| Class 1 — sand | 70 m¹ | € 18 | € 1,260 |
| Class 2 — clay | 40 m¹ | € 33 | € 1,320 |
| Class 3 — foundation | 10 m¹ | € 67 | € 670 |
| Lifting and relaying paving | 70 m¹ | € 12 | € 840 |
| Trial trench at crossing | 2 units | € 85 | € 170 |
| Total excluding VAT | € 4,260 | ||
| Average per linear metre | € 35.50 |
The agreement that matters
What if the ground turns out worse?
This is where trenching contracts founder: the ground proves heavier than at the survey and the argument starts. We settle it up front, in four rules.
- The class is determined and recorded per section at the survey.
- If the ground proves different, we stop work at that point and report it with a photograph and a measurement — before we dig on.
- Reclassification happens by agreement, using the same class rates listed above.
- No approval within the agreed window? Then we continue at an hourly rate, so the route does not sit idle.
What we do not do: send an after-the-fact variation invoice for metres that are already closed. If you can no longer verify them, you should not be billed for them either.
What the rate includes
Digging, backfilling with the excavated material, compaction, leaving the site tidy, the KLIC enquiry and locating, and contractors' all risks insurance with a KLIC clause.
What it does not include
- Supplying and laying cable, duct or ducting
- Reinstatement of asphalt or concrete
- Removal of surplus or contaminated soil
- Dewatering where the water table is high
- Traffic management and permits on public land
Not seeing your situation? Send the route, we will price it up and you will see the lines back in the quotation.
Don't work it out yourself.
Send your route and you will get a breakdown per class with every surcharge in it.